| |
FOR IMMEDIATE RELEASE
USAID/CDM Project in kandahar
“How I can pray to my
God,” my mother was crying one day –
Fazal Ahmad, director of Power Department (for the last six years) in
Kandahar explains. The entire Kandahar province did not have electricity
for one week a year ago. This meant that the pumps at the water department
were not working and more than 800.000 people in Kandahar province did not
have water. When the 80-year-old woman, Fazal Ahmad’s mother, wanted to
perform absolution before a prayer, even her son, the director of Power
Department was not able to do anything: It is our duty to wash our body
before we pray to God, otherwise our prayer will not be acceptable,
explains Fazal’s mother. She and 800.000 people from her province were in
a very miserable state due to the routine failures of the water supply
system. This is why Fazal Ahmad requested for CDM to install a diesel
generator for the water plant in Kandahar. The same request also came from
the Mayor, and Abdul Wahab Hamraz, director of CAWSS (Central Authority
for Water Supply and Sanitation) in Kandahar. In response, USAID emergency
programs with the help of CDM made it possible for an American generator
to finding its way to Kandahar water plant.
|

|
Water Problems in
Kandahar
Central Authority for Water
Supply and Sanitation (CAWSS) was designed by Japanese in 1950’s. It is
equipped with a transformer, four booster pumps, a reservoir, and two
backup generators. Gul Agha, the pump house operator has worked for CAWSS
for the past 20 years and went through all the regime changes. Gul Agha
explains: Whenever power was cut there was no water for the city. The
broken down backup generators could not supply the needed power and nobody
could repair them either due to the lack of spare parts. Even if they
could repair them, they used too much fuel and we would not afford it. In
addition, the transformer and the cabling could only power two pumps at a
time. People use to come to my house, and ask about water, they believed I
had it diverted to my house. But I also had to send my children to go more
than one kilometer to get water.
One of the solutions that
CAWSS provided was hauling water to neighborhoods in its only mobile water
tanker. When the tanker went around the city, the kids and women ran,
fighting and pulling each other, to get to the first of line. They had to
go a long distance to get water while carrying heavy containers and
sometimes staying in line for hours. Therefore, the children were usually
late for school. When power was re-established at night Gul Agha and all
his colleagues had to go back to water plant to distribute water.
|

|
No power, No water
Kajaki Hydroelectric Power
Station produces electricity for the two provinces of Kandahar (population
800,000) and Helmand (population 600,000). This station contains two 16.5
MV turbine generators which is not sufficient to support the population.
Fazal Ahmad, director of Power Department explains: The main problem in
our city is shortage of electricity and in turn water, since CAWSS depends
on us for powering their pumps. In the winter, the demand for power is
higher, so we have to shut down parts of the network to prevent overload.
Apart from that, we also have to shut off electricity for repairs. We have
only one hydroelectric dam, one transmission line and one substation for
distribution. When there is a problem, most districts do not have
electricity. Our power Lines are also old and overloaded. They break
often, and are not easily repaired. We also have difficulty getting to
power lines due to land mines and anti government factions that want to
destroy the power department’s capacity to turn the people against the
government. Apart from all this, due to the harsh drought over the past
four years, there has been much less power available from the dam.
This in turn resulted in lack of power and hence water at homes.
People were calling Fazal Ahmad and protesting shortage of power and
water. Even though it was the water department’s responsibility to
solve the water supply problem, the blame was always placed on the Power
Department and me.
|

|
An American company in
Afghanistan
Dynatek is a California
based American equipment provider (pumps, generators, instrumentations)
which is constantly increasing its presence in Middle East. Because of the
USAID waiver, the company found it very difficult to sell American
products in Afghanistan. Dynatek was the only American company in the
region that provided American industrial equipments.
Robert Mojave, director of
Dynatek Afghanistan Explains: Since we came to
Afghanistan, in March 2002, we have been in
constant contact with Foreign Aide agencies, various United Nations
agencies, USAID and Afghan Ministries to provide support for projects
relating to water and industrial infrastructure. However, German and
Japanese government agencies have a strict policy of buying German and
Japanese products. They have indicated to us clearly that American
companies have no chance of taking part in their projects. After German
and Japanese governments, ironically we got the worst response from USAID.
A USAID representative indicated to us that American products are
generally five times more expensive and have no support in the region!
Both statements are of course baseless. American products may cost more
(in short term) than Pakistani low quality equivalents but we are
competing and expanding all around the world. In addition, unlike
Pakistani suppliers that appear and disappear into thin air, we have been
around for the past 17 years and are committed to provide support for our
products. USAID representatives were even reluctant to provide us with
information on their projects so we could at least take part in the tender
process. The common replay was we do not have anything and call us in 14
days. At one point, we were told that there are no projects available
even though we knew they just signed a contract two days before. “I am not
sure if they were actively trying to mislead us or if they were genuinely
incompetent!” In either case, we were very frustrated and wrote a letter
to US Ambassador Finn, and our congressional representatives.
I believe this letter played some role in
Ambassador Finn’s decision to have an American generator for the USAID/CDM
project in Kandahar. I also like to
mention that unlike USAID, US commercial services were both very helpful
and forth coming. It is hard to believe these two agencies are both part
of the same department.
|

|
Buy American
Ken Choquette, Chief of
Party of CDM Afghanistan, arrived in Kandahar in August of 2002 to
implement USAID’s emergency water projects. Before his arrival CDM
engineers conducted an initial assessment and determined a new generator
and transformer for the plant were priorities. Choquette’s first step was
to meet with the mayor of Kandahar to confirm the problem: The mayor
was very weary of all the complaints. He specifically requested a quick
solution. Even though I was thinking there were higher priorities to
correct the problem in the long run, I assured the mayor to respond
quickly to eliminate his immediate concerns. At that time, I was not aware
of any USAID policy to buy American equipments as CDM had a waiver from
any such policy for Afghanistan.
The “buy American” policy was reinstated for the purchase of this
particular generator due to a complaint letter written to a US
congressional representative by Dynatek Machines Incorporated. I met
Robert Mojave and Fred Shafi (Dynatek representatives) in the Ministry of
Urban Development coordination meeting where they offered to provide us
with a quotation. I accepted the bid since they were the only American
company with a reasonable price and the commitment to follow through. Even
though a similar non-American generator could have been purchased from
another country in the region for less, Dynatek provided safe
transportation to Kandahar and the
important five year spare parts package. They even brought an engineer
directly from Cummins (Manufacturer) to certify the installation and train
the local staff on operational maintenance and minor repairs. Hence, this
generator is currently under a one-year manufacture warranty and it is
probably the only generator in Afghanistan with such a service. More over
Dynatek’s presence in Afghanistan further insured they could provide after
sales services.
|

|
The Assessment
In August of 2002 Dynatek
came to Kandahar for their assessment. It took them two weeks to gather
accurate information about existing equipments and the actual
configuration of the plant. During the past 25 years of ongoing war and
repeated changes in the government, most engineering drawings and
documentations were lost. In addition, the few plans that survived the
wars were outdated and inaccurate. There were undocumented changes made to
the plant by Russians, Taliban, and NGOs during the past 25 years. Robert
Mojave explains: It is difficult to find knowledgeable people in the
government. The very few people that partially know what is going on, are
difficult to identify and even harder to contact. I had to go to their
offices many times before I could find and speak to them. In the end after
gathering scores of conflicting information, I finally decided to excavate
the plant and visually inspect and verify the existing configuration. The
two Japanese generators were designed to work in tandem to generate enough
power for the plant. However, one was simply beyond repair and the second
generator even if repaired (which would cost too much) was unable to
handle the load. The rings and the engine block were badly worn and the
engine consumed enormous quantities of oil. There was also inadequate
compression in the engine causing reduced power and excessive fuel
consumption. The capacity of the transformer and the cables were also
inadequate to handle the load. Both the cables and the transformer were
constantly over heating. It appeared that they were replaced during the
Russian era since they were both made in
East Germany. The cables were unarmored, patched
up and were either placed in shallow ditches or on the surface creating a
major electric shock hazard. The Diesel fuel tank, which was probably made
in Pakistan, was leaking and creating a major environmental hazard,
especially in a water plant.
|

|
From California to
Kandahar
Finally a proposal was
submitted, and accepted by CDM and Dynatek started the process of bringing
an American generator to Afghanistan. Cummins (manufacturer) had a
six-week manufacturing time and transporting the generator from US would
take at least another six weeks. This would stretch the projects execution
period beyond the deadline. Robert had to persuade another division of
Dynatek to give up a generator, which was already built and intended for a
hospital in Southern California. They agreed and the generator was shipped
from long beach California to Dubai, and flown from there to Kabul. From
Kabul to Kandahar, the generator had
to be transported by truck.
We had three options for
getting the generator to Kandahar.
1. We could either ship
it to Russia and then rail it through Turkmenistan to northern Afghanistan
and truck it through Herat to Kandahar. This route was both safe and cost
efficient but it would take too long.
2. Ship it to Pakistan
and then truck it through southern Afghanistan to Kandahar. This route was
also economical but there were some safety concerns in southern
Afghanistan. In addition, corrupt border guards in both Pakistan and
Afghanistan could cause major delays.
3. Ship it to Dubai and
then fly it to Kabul and from there truck it to Kandahar. This route was
relatively safe and fast but very expensive. It increased the generator
cost by about 20 percent.
The road from Kabul to
Kandahar was horrific, and the trucks that transport goods through this
road are not used to transporting sensitive equipments. Fred and I decided
to escort the truck personally From Kabul to Kandahar to keep an eye on
the driver. We spent 51 hours driving a 500 kilometers (about 300 miles)
distance. We had severely underestimated the condition of the road. In
some stretches, we had to force the truck to slow down to five kilometers
(3 miles) per hour for hours on end. The only reason that cars stay on the
road rather than going off-road was presence of land mines. On the second
day of the trip, we were stopped at a checkpoint in Zabul province and
were threatened by a 16 years old soldier aiming an AK 47 at my head and
releasing the safety. Fortunately his commander came and pulled him away.
Finally, after three days of hell, the generator arrived in Kandahar.
|

|
Generator installation
Dynatek replaced the
generators, the transformer, and most of the cables and control
equipments. They also produced detailed plans for the entire compound.
They constructed cable conduits, a
transformer pad, and a new tank and enclosure. Dynatek also replaced a
high-tension electric pole and isolator switch. Robert Mojave explains:
For a project this scale, there is a shortage of suitable equipments in
the country. Unloading a 7200 Kg generator from the truck and placing it
on the pad took us two days and much nerve. In US, it would take one
forklift and five minutes. We had to use
two ten tones manual cranes and 30 people to lift
and position the generator on the pad. The installation of the 600 kg
muffler required even greater care. The muffler had a special heat
resistant paint that if scratched could not be repaired in Afghanistan. We
had to use plastic ropes to protect the paint. If the muffler would slip,
it would definitely destroy the generator and probably cause severe injury
or even death of our workers. This of course was our primary concern. We
had to take safety of labors into account and it appeared we were a lot
more concerned about their safety than the laborers themselves. It took
much effort to explain to the
Afghan supervisors that safety is a
priory. However, due to lack of appropriate equipments I was forced to
accept an Afghani master
craftsman’s idea for him to clime the muffler to maintain the balance and
attach the support belts. He was later sitting up there and smoking a
cigarette. We completed the generator installation without any incidents.
|
 |
Working with Afghan
labor
Any work that was done
unsupervised almost always had to be re-enacted, even though the same
people could do a superb job once they were told exactly what they needed
to do and were supervised during the whole process. Construction
activity in Afghanistan is not as easy as it initially seems. Even though
labor and material are very economical, the afghan labor needs constant
supervision. I had to constantly monitor the work to make sure they do not
destroy the equipments or take shortcuts. This was a relatively small
project thus we did not have enough time to train the supervisors
properly. As long as they got the job done for that moment, they were
satisfied. They paid absolutely no attention to details, static, and
quality of work. The whole installation took about two weeks including a
test phase. We did not change the 20 years old pumps and panels. There
were four different groups of equipments patched up in the plant. Some
original Japanese, some East German from Russian era, some Iranian-Chinese
hybrids from the Taliban time, and some various equipment installed by
different NGOs. We had to connect all of them together, switch from the
old system to the new one, and make it all work in one afternoon so there
was no major interruption to the services. What in US is considered a
normal day’s work, in Afghanistan, with substandard, old and patched up
equipments is considered a substantial achievement. |

|
Working with the local
Government departments
Kandahar Power Department
does not have sufficient isolators in the network grid. This prevents most
parts of the network from being disconnected selectively. Electric
department has to shutdown the entire city to repair some segments of the
network. There is also no communication with people at the tower and hence
there is no way to ensure that the electricity remains shut .Therefore
Workers do not have enough time to do a proper job. Sometimes we were torn
between putting a laborers life further in danger by forcing them to work
properly, or accept a substandard work and put the life of others in
danger in the future. When the Power department technicians installed the
20 KV high-tension cables and the isolator switch improperly. We had to
force them to reinstall it again, despite our concerns for their safety.
|
|
Performance based
compensation without discrimination
During the whole process of
installation, Dynatek was trying to teach American management to Afghani
contractors. Jan Mohammad is an example of this. Jan Mohammad was not able
to find a job on the labor market. He was trying very hard every day but
he did not have a chance. Jan Mohammad has only five fingers in both hands
and in a labor market flooded with healthy unskilled labor, no one would
give him a chance. Having a sick wife and no money for medicine, he walked
into the water plant looking for work and was personally hired by Robert
Mojave. He turned up to be one of the hardest working people in the group.
Robert Mojave Explains: The contractors always pick the healthy looking
laborers but once you are selected, As long as you show up, you
will be paid the same amount. Furthermore, it is considered boorish to
fire someone just because they do not work. This is the type of management
that has been embedded into the work culture during the communist era.
This discourages hard working people and promotes steeling from work. This
is specially evident among bureaucrats and government employees. The
supervisors generally do not care either. They simply assigning more work
to the hard working people and ignore those who do nothing. Starting with
12 laborers, close to the end we ended up with six people but were getting
more work done. I was constantly monitoring the workers and by the second
day had a good idea about their attitude and performance. The hardest
working laborers were getting bonuses (up to three times their pay) and
those who did not work were fired. Out of this six remaining laborers two
were handicapped. One had lost part of his foot from a land mine explosion
and the other had a total of five-fingers in both hands. Those two turned
up to be amongst the hardest working people we had. The person with five
fingers was initially sick from malnutrition, but he
was still working very hard. After the
installation, I gave him a temporary job cleaning the plant until I could
find him a better job. I wanted to show a little percentage of the
population the way things can be done. Give a person a chance even if they
have some handicap. Compensation based on performance and without
discrimination. This is what made this project a success to me.
|

|
What happens now?
Gul Agha: Now that we have a
generator, we feel a lot more comfortable. However, we still have a
problem with leaks in the network. When there is a power failure, there is
no pressure in the network and because of leaks, contaminated water
re-enters the pipes. When power is resumed, this contaminated water is
pumped to the people. The network was built in 1952, and was badly damaged
during the war. With the new generator, we have the pressure, but we still
have the problem of contamination.
Fazal Ahmad: I was
excited when I saw the generator and the transformer. Our city is
crippled, No legs, no arms. Any small improvement gives us hope. We are
not lazy, but we do not have the means. Just help us to stand on our own
feet and we will do the rest. We still have problems with our electricity,
but at least when we have to shutdown the electricity for repairs, the
water plant has a generator and can supply water for the city.
|
|
|